|
26-E-0000-0221
| US Army Corps of Engineers |
Proposed federal action includes five elements related to dredging and placement of material: (1) the creation of a new navigation corridor that encompasses approximately 5,500 acres of Pamlico Sound; (2) the addition of two open-water dredged material placement areas north of Big Foot Slough Channel and north of Nine Foot Slough; (3) placement of dredged material on Beacon, North Rock, and Shell Castle Islands; (4) placement of dredged material into the littoral zone via hydraulic pipeline; and (5) placement within naturally deep-water areas in Big Foot Slough Channel or Teaches Hole Channel.
|
05/13/2026
|
06/11/2026
|
|
26-E-0000-0222
| Harnett County |
Proposed Action includes a 500-foot runway and taxiway extension, widening the runway by 25 feet, and installing a new approach lighting system. Associated work includes grading of the associated runway safety and object free areas, relocation of the airport perimeter road and fencing, construction of stormwater controls, acquisition of borrow material, and installation/temporary use of staging areas, haul roads, and sedimentation and erosion control features.
|
05/13/2026
|
06/11/2026
|
|
26-E-0000-0223
| Town of Waxhaw |
Proposes to widen North Broome Street (NC 16) to three lanes between North Church Street and South Main Street (NC 75), totaling approximately 0.4 miles. The project will also include intersection improvements, construction of sidewalks, and upgrades to existing pedestrian facilities along the North Broome Street corridor.
|
05/13/2026
|
06/11/2026
|
|
26-E-0000-0224
| Town of Waxhaw |
Project proposes to extend Waxhaw Parkway West by approximately 0.3 miles from the existing western terminus and connect to a proposed roundabout at Waxhaw Mavin Road (S.R. 1307). The project will also include construction and improvement of pedestrian facilities along Waxhaw Parkway between providence Road South (N.C 16) and WaxJ1aw Marvin Road (S.R. 1307), totaling approximately 1.0 mile. The proposed roundabout at Waxhaw Marvin Road (S.R. 1307) will not be constructed as part of this project.
|
05/13/2026
|
06/11/2026
|
|
26-E-0000-0225
| Wilkes County |
To continue providing for the waste management needs of its residents, Wilkes County purchased an approximately 300-acre tract (Eller Property) located adjacent to the east of the existing landfill property. An area of approximately 110 acres, including part of the Eller Property tract, plus portions of tracts north of the Phase 6 area, which the County already owned, is proposed for expansion of the landfill. The expansion will include three new waste cells totaling 20.6 acres, including Phase 7 (6.2 acres), Phase 8 (5.5 acres), and Phase 9 (8.9 acres), which are shown on Attachment 1, Drawing 1. The three new phases are each expected to add approximately 5–6 years of landfill capacity. If approved, we anticipate that Phase 7 will be constructed in 2030-31, Phase 8 in 2035-37, and Phase 9 in 2040-2043. Proposed Phases 7 and 8 lie predominantly within the existing landfill facility boundary, so the expansion area would serve primarily as a buffer for these cells.
|
05/13/2026
|
06/11/2026
|
|
26-E-0000-0226
| Burlington-Alamance Airport Authority |
The Proposed Action projects (Figure 1.1-1, page 2) are intended to provide a new terminal area that is more conducive to the existing and forecast operations at BUY. The Proposed Action shown as Phase 1 in Figure 1.1-1 (page 2) includes a new 5,500-18,500 square foot terminal building; final dimensions will be determined prior to construction. A 51,100 square-yard apron and taxilane would be constructed adjacent to the terminal. A portion of Rocklane Drive will be closed prior to the Phase 3 automobile access road to accommodate the terminal apron development. The existing terminal building would be repurposed in the interim, it is proposed to be dedemolished for future hangar development as needed per the Airport Master Plan Update (AMPU). The apron would continue to accommodate based aircraft until future hangar development will replace these facilities.
|
05/26/2026
|
06/24/2026
|
|
26-E-0000-0227
| NC Utilities Commission |
(NCUC Docket No. SP-12717 Sub 6) Application of Fayetteville Public Works Commission for a Certificate of Public Convenience and Necessity to Construct a 4.875 MW Solar Facility in Cumberland County, North Carolina.
|
05/27/2026
|
06/25/2026
|
|
26-E-0000-0228
| NC Department of Transportation, Div 10 |
Project proposes interchange improvements including ramp improvements and minor widening at the I-485/Idlewild Road (S.R. 3174) interchange. The coordinates of this project are approximately 35.126796, -80.656719.
|
05/28/2026
|
06/26/2026
|